|
||||||||||||||||||||||||||||||||||||
|
|||||||||||||||
|
Utilization of Digital Automation Architecture Can Slash Nearly $20 Million from New Coal Plant Construction Costs
New study shows that digital bus technologies can significantly reduce costs to build an $840 million greenfield 600-megawatt pulverized coal-fired supercritical power plant
PITTSBURGH, PA (December 9, 2003) Integrating digital bus technology into the design of new coal-fired power plants can result in total project cost reduction of as much as $20 million for a 600-megawatt coal-fired plant according to a new plant construction study released today at POWER-GEN International 2003. Emerson, who commissioned the independent study, explained the purpose and chosen study methodology. “PlantWeb® , Emerson's digital plant architecture, has been installed in other industries around the world and has proven to save 30 percent or more in installed automation costs,” said Ann Pauley, president of the Power & Water Solutions industry center of Emerson Process Management. “We were confident that the digital approach would deliver superior automation and major cost reductions for construction of coal-fired power plants. We determined that contracting a rigorous, quantified third-party study based on engineering and construction practices was a viable, unbiased method of demonstrating the possibilities.” "The Economic Impact of Digital Bus Technology on New Plant Construction,” conducted by JDI Contracts Inc., identified and compared five categories of costs: engineering, construction, startup, system selection and overheads. These costs were applied to two different approaches – traditional and digital bus-based – to instrumentation & control (I&C) system implementation for an $840 million greenfield 600-megawatt pulverized coal-fired supercritical power plant. According to the study, utilization of digital I/O bus technology can slash up to $20 million – or 2.35 percent – off the entire project budget. “This study details a methodology that gives stakeholders in the utility industry the best of both worlds: the ability to save millions of dollars in construction costs while also delivering a highly automated plant featuring state-of-the-art I&C systems,” said Roger Hoyum, author of the study. The traditional approach used an Engineer-Procure-Construct (EPC) model and selected an I&C system through an evaluated bid process. The installation utilized dedicated field cables to hardwire non-intelligent field devices to I/O cards. The digital bus approach, which used an alternative selection process – PEpC (Procure strategic suppliers, Engineer, procure balance of plant and Construct) – featured an integrated system of high-speed communications networks, intelligent field devices and bus I/O technologies. The digital bus approach also used traditional I/O for certain high-speed and safety-related loops. Defining the Study Next, researchers placed control system cabinets and Motor Control Centers (MCC) on GA drawings. Design criteria were developed for both approaches, including construction labor costs, tray conduit and cable lengths, and material costs. Individual design parameters were assigned to all I/O points in the study to complete the construction estimate. Device upgrade costs from smart transmitters, digital I/O and intelligent motor interfaces were estimated for the digital installation. Plant checkout and startup tasks were defined for each I/O type, as well. A plant construction schedule and budget was created to estimate a total spending curve. From this, researchers developed a construction financing methodology to estimate interest during construction (IDC), which is the cost to borrow money to build the facility. Inflationary escalation was estimated based on typical utility accounting methods.Fixed overhead costs were assigned to all construction and startup line items, and included administrative and general support, construction management, contingency, contractor indirect charges, freight, project management, spares and sales tax. Variable overheads included inflation escalation and IDC at a rate of 3 percent and 6 percent, respectively, both compounded calculations. Digital Bus Technology Adds Value, Cuts Costs Engineering Construction Startup “But, even more importantly, reducing the time spent on the critical path to unit synchronization leads to much more significant savings in IDC,” he continued. System Selection Overheads Implications for the Industry “By making it possible to save millions of dollars while delivering a state-of-the-art plant, the digital bus-based approach outlined in this study is setting a new standard for plant construction,” said Hoyum. “And with so much at stake in projects such as these, it is an approach utility stakeholders can't afford to ignore.” About JDI Contracts Inc.JDI Contracts Inc. (www.jdicontracts.com) is a privately owned Minnesota-based consulting firm serving industrial and commercial customers. Services include project development and management, multi-disciplined engineering support, and construction management. JDI Contracts Inc. specializes in change management, allowing customers to concentrate on core business operations. About Emerson Process ManagementEmerson Process Management (www.emersonprocess.com),
an Emerson business, is a leader in helping businesses automate
their production, processing and distribution in the power, water
and wastewater treatment, chemical, oil and gas, refining, pulp
and paper, food and beverage, pharmaceutical, and other industries. About EmersonSt. Louis-based Emerson (www.gotoemerson.com) is a global leader in bringing technology and engineering together to provide innovative solutions to customers in process control; electronics and telecommunications; industrial automation; heating, ventilating and air conditioning; and appliance and tools. Sales in fiscal 2003 were $14 billion. Ovation, SureService, SmartProcess, PlantWeb, Fisher, Micro Motion, Rosemount, AMS™ Suite and DeltaV are marks of Emerson Process Management. Other marks are the property of their respective owners. |
|
||||||||||||||
| |
|||||||||||||||
|